Here is the latest update from Liberia!
The work starts at 7:30 am and finishes at 7:15 pm.
There are 12 people working on site + two people providing security service.
Last week we were mainly working on library, toilet and septic tank.
Building “A” and "B" are 90% completed.
We are close to finalize Gbarnga Learning Community Center.